The Hunter Facilities department has been working diligently to insure a speedy recovery from flooding damage the Brookdale Campus sustained during Superstorm Sandy. The photos contained on this page show various aspects of the work involved.

Below:  The new rooftop chiller arrives.  (Photos added 5/10/13)

Below:  Physical Therapy class is ready to get started!    (Photos added 4/2/13)

ptstart1
ptstart2
ptstart3

Below:  Final touches being added to the Physical Therapy teaching space on 3/8/13---the day of its reoccupancy.  (Photos added 4/2/13)

ptfinal1
ptfinal3
ptfinal4
ptfinal5

Below:  Physical Therapy teaching space as it nears finishing, soon to be ready for reoccupancy.  (Photos posted 3/6/13)

ptspace1
ptspace2
ptspace3
bkdalepool
3/6/13: The Brookdale pool nears completion--shown here refilled and outfitted with new equipment. The pool will be ready for use once testing and commissioning is complete.
ptbuild1
Physical Therapy Department: Ceiling and floor tiles are being installed throughout the space. Painting is nearly complete. Furniture is being delivered for an expected March 11, 2013 reoccupancy. (Photo posted on 2/26/13)
ptbuild2
(Photo posted on 2/26/13)
majelectricbkdale
(Posted 2/19/13) Major electrical work started Saturday to install new main electrical distribution panels for each campus building and new switchgear cabinets (shown above) in the main switchgear room. The work is proceeding in phases starting with the West Building (completed on Saturday, 2/16/13) and moving to the North Building, and then the East Building. Each phase lasts approximately 12 hours and is further compartmentalized to minimize power disruption to individual spaces. This work is a major component of the recovery work related to the superstorm. <br />

sandy1
The campus receives a delivery of the main electrical switch boxes for the entire campus. Since Superstorm Sandy, the campus has been running on a temporary set-up of electrical switches.
 

sandy2
Main electrical switches for the entire campus, awaiting installation.
sandy3
This electrical switching equipment was badly damaged by Superstorm Sandy flood waters. New switches are replacing this equipment.